Wind turbine with blue sky

Case study

Temporary power provision for Borssele 1 and 2

Overview

OEG Renewables topside service line signed a contract with Ørsted for the provision of temporary power solutions, offshore personnel and crew transfer vessels during the turbine commissioning phase of the Borssele 1 and 2 offshore wind farm.

The construction of Borssele 1 and 2 Offshore Wind Farm consisted of 94 turbines generating 752MW, making it the largest offshore wind farm in the Netherlands and the second largest operating offshore wind farm in the world. Borssele 1 and 2 provides enough green electricity to power one million Dutch households.

Borssele 1 and 2 is Ørsted’s first offshore wind farm in the Netherlands.

Client

Ørsted

Location

Vlissingen, The Netherlands

MV on Borssele 2
Temporary Power Borssele 1 and 2
Manor Enterprise Borssele
×

Gallery view

Challenges

The main challenges faced by the client was to reduce construction time and the high level of multi-discipline personnel at site.

Workscope

Ørsted contracted OEG Renewables topside service line to provide temporary power during the turbine commissioning phase of the 94 Siemens Gamesa Renewables 8.0-167 type turbines at the Borssele 1 and 2 offshore wind farm.

Solution

OEG Renewables supplied modular temporary power packages, consisting of a 116 kVA generator, custom-built fuel tank, transformer and bespoke lifting frames. The OEG Renewables owned Manor Venture, Manor Initiative and Manor Enterprise, alongside associated offshore personnel, were also contracted by Ørsted to maintain and refuel the offshore generators.

Based out of the port of Vlissingen in The Netherlands, the fleet maintained the 44 generators required during the construction phase of the windfarm; at peak activity OEG Renewables provided three teams of three personnel over each 24-hour period.

OEG Renewables personnel created bespoke lifting plans & equipment to enable the generators positioned offshore to be recycled between turbines throughout the project. Over the course of the project, the vessels completed over 4,400 safe transfers of personnel. On completion of the temporary power requirement, all sets were demobilised from their respective transition pieces; all 44 units were then delivered to OEG Renewables' home port of Portland, Dorset, UK.

Testimonial

We successfully delivered the complete temporary power solution during the construction phase of the Borssele 1 and 2 wind farm.

We built on our existing relationship with Ørsted during the course of the project and are looking forward to working with them again in the future.

- Simon Oakley
Project Manager at OEG Renewables